05/31/2022

12:07 PM 2.00 hours (Project: BBG)
Meeting Pembahasan HRIS Approval sesuai Struktur Organisasi PT Bayu Buana Gemilang ikawati basri
12:03 PM 0.50 hour (Project: BBG)
Guide User Closed Pajak Karyawan resign ikawati basri
11:58 AM 1.00 hour (Project: BBG)
Update StartDate, EndDate, StartDeduction & EndDeduction Absence Quota Cuti Tahunan 2022 ikawati basri
11:07 AM 2.00 hours (Project: BBG)
Meeting Koordinasi Case-Case di BBG ikawati basri
10:55 AM 0.50 hour (Project: BBG)
query report cuti karyawan dari database ikawati basri
10:45 AM 2.00 hours (Project: BBG)
Fixing Case Approval ESS masih belum sesuai dengan Struktur Organisasi BBG ikawati basri
10:25 AM 2.00 hours (Project: BBG)
Fixing case Approval ESS Travel untuk karyawan yang tidak punya DS1 ikawati basri
10:13 AM 0.50 hour (Project: BBG)
Preparing Report untuk Guidance user BBG ikawati basri
10:10 AM 0.50 hour (Project: BBG)
Report Workflow cuti karyawan yang belum finish ikawati basri

05/13/2022

05:52 PM 0.50 hour (Project: BBG)
Guide User untuk penarikan Report Unfinished Workflow ESS Leave ikawati basri
09:29 AM 1.50 hour (Project: BBG)
Meeting Terkait Case PPH April - Proofing Pajak ikawati basri
09:21 AM 2.50 hours (Project: BBG)
Proofing Tax Case PPH BBG April ikawati basri

05/11/2022

05:54 PM 0.50 hour (Project: BBG)
Meeting Terkait Beberapa Catatan Case ikawati basri
05:53 PM 1.00 hour (Project: BBG)
Proofing Pajak Case PPH Bulan April Besar ikawati basri
 