Project

General

Profile

Activity

From 04/14/2023 to 05/13/2023

05/12/2023

11:10 AM 2.00 hours (Feature #2167 (Closed): Kondisi cabang di flow address)
Kondisi cabang di flow address M Azid Wahyudi

05/10/2023

05:42 PM 5.00 hours (Project: BANK WOORI SAUDARA)
[ESS-Overtime] Selisi perhitungan lembur Johanes Christian Kurni
05:40 PM 8.00 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] Mapping parameter tarif yang baru, form accomodation, penambahan flow mail task dan flow resived Johanes Christian Kurni
05:35 PM 1.00 hour (Project: BANK WOORI SAUDARA)
[ESS-Travel] Field pos table header Johanes Christian Kurni

05/09/2023

12:34 PM 3.50 hours (Bug #2161 (Closed): [ESS-Overtime] Validasi hari libur bedasarkan grade dan class)
[ESS-Overtime] Validasi hari libur bedasarkan grade dan class M Azid Wahyudi
10:39 AM 2.30 hours (Bug #2160 (Closed): [ESS-Travel] FieldPos)
[ESS-Travel] FieldPos M Azid Wahyudi

05/08/2023

05:48 PM 8.00 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] fielpos, [ESS-Overtime] update perubahan ketentuan pengajuan lembur berdasarkan grade dan class Johanes Christian Kurni
05:02 PM 8.00 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] fieldpos, review hasil dari pengecekan dari pihak bws untuk report wage type recap COA dan General Johanes Christian Kurni

05/04/2023

06:12 PM 2.30 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] Posting ke master data Johanes Christian Kurni
03:30 PM 5.30 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] Testing skenario tarif penjalanan dinas dalam negri dan luar negri sesuai jarak dan grade karyawan Johanes Christian Kurni

05/03/2023

05:50 PM 8.00 hours (Project: BANK WOORI SAUDARA)
Perbaikan dan pengetesan pada report wage type recap, testing flow approval, perbaikan dan testing parameter cost pad... Johanes Christian Kurni
03:05 PM 1.30 hour (Bug #2149 (Closed): [ESS-Travel] Form body - Field Alternate)
[ESS-Travel] Form body - Field Alternate M Azid Wahyudi
11:26 AM 1.30 hour (Bug #2145 (Closed): [ESS-Travel] Cost)
[ESS-Travel] Cost M Azid Wahyudi
10:29 AM 1.30 hour (Bug #2142 (Closed): [ESS-Travel] Flow Approval)
[ESS-Travel] Flow Approval M Azid Wahyudi
10:05 AM 1.00 hour (Feature #2147 (Closed): Kolom Cost Group (CG) di Report Wage Type Recap)
shofwan shiddiq

05/02/2023

05:26 PM 4.00 hours (Project: BANK WOORI SAUDARA)
Perbaikan hasil review untuk report Review Wage Type Recap General Report vs COA - Expense Code Report Johanes Christian Kurni
05:09 PM 4.00 hours (Project: BANK WOORI SAUDARA)
[ESS-Travel] Flow approval, form cost Johanes Christian Kurni

04/28/2023

02:27 PM 5.00 hours (Bug #2066 (Closed): [HR-Time Management] Time Data - Absence)
[HR-Time Management] Time Data - Absence M Azid Wahyudi

04/27/2023

03:36 PM 6.00 hours (Bug #2141 (Closed): [ESS-Exit Clearance] Mail Task)
[ESS-Exit Clearance] Mail Task M Azid Wahyudi

04/26/2023

05:44 PM 2.00 hours (Project: BANK WOORI SAUDARA)
ESS Exit Clearance M Azid Wahyudi

04/18/2023

11:26 AM 4.00 hours (Bug #2137 (Closed): [ESS-Staff Requisition] Mail Task)
[ESS-Staff Requisition] Mail Task M Azid Wahyudi
 

Also available in: Atom