Bug #2515: [GENERATE USER] generate us... Bug #2515: [GENERATE USER] generate user tidak berjalan pada saat execute

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/24/2024
Assignee: Muhammad Bintar
Priority: High
Bug #2513: [ESS-WORKFLOW REPORT] perba... Bug #2513: [ESS-WORKFLOW REPORT] perbaikan pada menu workflow report

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/23/2024
Assignee: Muhammad Bintar
Priority: Normal
Bug #2512: [ESS-PMS]input data self sc... Bug #2512: [ESS-PMS]input data self score kalau diisi semua 5 maka kpi summary nya jadi 5.01 seharus nya 5

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/22/2024
Assignee: Muhammad Bintar
Priority: Normal

20

4

21

22

Bug #2512: [ESS-PMS]input data self sc... Bug #2512: [ESS-PMS]input data self score kalau diisi semua 5 maka kpi summary nya jadi 5.01 seharus nya 5

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/22/2024
Assignee: Muhammad Bintar
Priority: Normal
Bug #2518: [ESS-PMS FINAL] pengisian f... Bug #2518: [ESS-PMS FINAL] pengisian form harus lengkap untuk creator, ds1 dan ds2

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/22/2024
Due date: 01/24/2024
Assignee: Muhammad Bintar
Priority: High
Bug #2516: [HR-PMS Monitoring] perbaik... Bug #2516: [HR-PMS Monitoring] perbaikan pada report PMS Monitoring

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/22/2024
Due date: 01/23/2024
Assignee: Muhammad Bintar
Priority: Urgent

23

Bug #2516: [HR-PMS Monitoring] perbaik... Bug #2516: [HR-PMS Monitoring] perbaikan pada report PMS Monitoring

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/22/2024
Due date: 01/23/2024
Assignee: Muhammad Bintar
Priority: Urgent
Bug #2513: [ESS-WORKFLOW REPORT] perba... Bug #2513: [ESS-WORKFLOW REPORT] perbaikan pada menu workflow report

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/23/2024
Assignee: Muhammad Bintar
Priority: Normal
Bug #2520: [ESS-ARCHIEVE]menu archieve... Bug #2520: [ESS-ARCHIEVE]menu archieve tidak berfungsi

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/23/2024
Due date: 01/26/2024
Assignee: Muhammad Bintar
Priority: High

24

Bug #2518: [ESS-PMS FINAL] pengisian f... Bug #2518: [ESS-PMS FINAL] pengisian form harus lengkap untuk creator, ds1 dan ds2

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/22/2024
Due date: 01/24/2024
Assignee: Muhammad Bintar
Priority: High
Bug #2515: [GENERATE USER] generate us... Bug #2515: [GENERATE USER] generate user tidak berjalan pada saat execute

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/19/2024
Due date: 01/24/2024
Assignee: Muhammad Bintar
Priority: High

25

26

Bug #2520: [ESS-ARCHIEVE]menu archieve... Bug #2520: [ESS-ARCHIEVE]menu archieve tidak berfungsi

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/23/2024
Due date: 01/26/2024
Assignee: Muhammad Bintar
Priority: High

27

5

28

29

30

Bug #2538: [HR-PMS Monitoring] perbaik... Bug #2538: [HR-PMS Monitoring] perbaikan pada report PMS Monitoring

Project: BANK MEGA SYARIAH ES Bugs
Status: QA Test
Start date: 01/30/2024
Due date: 02/05/2024
Assignee: Muhammad Bintar
Priority: High