Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 2446.70

Date User Activity Issue Comment Hours
02/21/2022 M Azid Wahyudi Project Feature #896: [Report Attendance Recap] Perubahan Nama Field [Report Attendance Recap] Perubahan Nama Field 1.00 Actions
02/18/2022 Tri Rizqiaty Project Feature #882: [Report Payroll] Report Akumulasi Cuti Tahunan dan Cuti Besar Create Report Bekal Cuti BKT 5.00 Actions
02/17/2022 Tri Rizqiaty Project Feature #882: [Report Payroll] Report Akumulasi Cuti Tahunan dan Cuti Besar Create Report Bekal Cuti BKT 3.00 Actions
02/17/2022 Mega Yunita Project Membuat FRD Project PERTALIFE 2.00 Actions
02/17/2022 Mega Yunita Project Setting PMS di project BKT 2.00 Actions
02/17/2022 Mega Yunita Project Setting PMS di project Pertalife 4.00 Actions
02/16/2022 Mega Yunita Project Setting PMS di project BKT 4.00 Actions
02/16/2022 Mega Yunita Project Setting PMS di project Pertalife 4.00 Actions
02/15/2022 Mega Yunita Project Setting PMS di project Pertalife 4.00 Actions
02/15/2022 Mega Yunita Project Setting PMS di project Pertalife 4.00 Actions
02/15/2022 Mega Yunita Project Membuat User dan menentukan role untuk Project BKT 0.30 Actions
02/14/2022 Mega Yunita Project Setting PMS di project Pertalife 2.00 Actions
02/14/2022 Mega Yunita Project Testing BKT 2.00 Actions
02/14/2022 Mega Yunita Project Monitoring redmine dan QA Test 4.00 Actions
02/11/2022 Mega Yunita Project Testing Project BKT 4.00 Actions
02/11/2022 Mega Yunita Project Testing dan memperbaiki settingan Time Management dan HR Administration project BKT 4.00 Actions
02/10/2022 Mega Yunita Project Memperbaiki settingan setelah UAT Bank Kalteng 4.00 Actions
02/10/2022 Mega Yunita Project Memperbaiki settingan BKT 1.00 Actions
02/10/2022 Mega Yunita Project Memperbaiki settingan BKT 1.00 Actions
02/10/2022 Mega Yunita Project Memperbaiki settingan setelah UAT Bank Kalteng 2.00 Actions
02/10/2022 M Azid Wahyudi Project Feature #727: Time Management - Late Time Management - Late 1.00 Actions
02/09/2022 Mega Yunita Project Testing dan Setting Parameter BKT 4.00 Actions
02/09/2022 Mega Yunita Project Testing PMS BKT 2.00 Actions
02/09/2022 Mega Yunita Project Setting Parameter Bank Kalteng 2.00 Actions
02/08/2022 Mega Yunita Project Testing dan Input data PMS BKT 4.00 Actions
(601-625/681) Per page: 25, 50, 100