Project

General

Profile

Activity

From 07/09/2022 to 08/07/2022

08/05/2022

05:47 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel - New flow Fiona Avangeline Jonathan

08/04/2022

06:10 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
Support UAT phase 2 M Azid Wahyudi
05:54 PM Bank Kalteng (Phase 2) 7.00 hours (Project: Bank Kalteng (Phase 2))
OM BKT Fiona Avangeline Jonathan

08/03/2022

03:56 PM Bank Kalteng (Phase 2) 7.00 hours (Project: Bank Kalteng (Phase 2))
Follow up hasil UAT Fiona Avangeline Jonathan
09:07 AM 8.00 hours (Project: BANK KALTENG)
Testing & preparation UAT PMS, Talent, Compensation, recruitment Fachrul Hardianto
09:02 AM 8.00 hours (Project: BANK KALTENG)
UAT External Bank Kalteng Fachrul Hardianto
09:01 AM 8.00 hours (Project: BANK KALTENG)
UAT External Bank Kalteng Fachrul Hardianto

08/02/2022

06:08 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
support UAT phase 2 , fixing bug modul PMS , BKT (modul recruitment, modul training) M Azid Wahyudi
05:57 PM Bank Kalteng (Phase 2) 2.00 hours (Bug #1412 (Closed): [Reqruitment Management] Report Vacancy List tidak tampil)
[Reqruitment Management] Report Vacancy List tidak tampil M Azid Wahyudi
04:39 PM Bank Kalteng (Phase 2) 1.00 hour (Bug #1422 (Closed): [HR - Recruitment Management] Filter di Report Applicant Activity by Assignment tidak berfungsi)
[HR - Recruitment Management] Filter di Report Applicant Activity by Assignment tidak berfungsi M Azid Wahyudi
03:30 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
UAT Phase 2 Fiona Avangeline Jonathan
02:55 PM Bank Kalteng (Phase 2) 4.00 hours (Bug #1398 (Closed): [Report PMS] Menampilkan Report PMS per Individu)
[Report PMS] Menampilkan Report PMS per Individu M Azid Wahyudi
10:12 AM Bank Kalteng (Phase 2) 1.00 hour (Bug #1397 (Closed): [HR PMS] Data yang tampil masih kode)
[HR PMS] Data yang tampil masih kode M Azid Wahyudi

08/01/2022

06:35 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Support BKT UAT phase 2 , Rotho (modul time management) M Azid Wahyudi
04:12 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
UAT Phase 2 Fiona Avangeline Jonathan

07/29/2022

04:20 PM Bank Kalteng (Phase 2) 1.30 hour (Bug #1377 (Closed): [HR - Training Management] Nama Office tidak sesuai)
[HR - Training Management] Nama Office tidak sesuai M Azid Wahyudi
02:52 PM Bank Kalteng (Phase 2) 5.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/28/2022

06:41 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
aceh (Support request Client) , BKT (PMS goal setting , review , final & travel) , BMS(Travel editGrid for web mobile... M Azid Wahyudi
06:36 PM Bank Kalteng (Phase 2) 2.00 hours (Support #1399 (Closed): [ESS Travel] Mail Notif Supervisor)
[ESS Travel] Mail Notif Supervisor M Azid Wahyudi
05:58 PM 3.00 hours (Project: BANK KALTENG)
Meeting BKT Johanes Christian Kurni
02:56 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Pendampingan Trial Phase 1 BKT Fachrul Hardianto
02:55 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Pendampingan Trial Phase 1 BKT Fachrul Hardianto
02:49 PM Bank Kalteng (Phase 2) 2.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Meeting Progress BKT Fachrul Hardianto
02:48 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan meeting Pre-UAT Bank Kalteng modul Talent & Training Fachrul Hardianto
02:41 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom meeting Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:39 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom meeting Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:39 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:32 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan Pre-UAT Bank Kalteng modul Budgeting & Recruitment Fachrul Hardianto
02:31 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Pre-UAT Bank Kalteng modul Budgeting & Recruitment Fachrul Hardianto
02:27 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
Testing & preparation PRE-UAT Mecical & Travel Fachrul Hardianto
02:24 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Bank Kalteng Pre-UAT Modul Medical & Travel Fachrul Hardianto
12:13 PM Bank Kalteng (Phase 2) 4.00 hours (Feature #1402 (Closed): [ESS PMS] Bobot Perhitungan KPI dan Competency)
[ESS PMS] Bobot Perhitungan KPI dan Competency M Azid Wahyudi

07/27/2022

05:12 PM 3.00 hours (Project: BANK KALTENG)
BKT Rekruitmen fernando sergio rumbayan
11:43 AM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
09:47 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
ess travel , PMS , report2 M Azid Wahyudi

07/26/2022

04:54 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
04:54 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan
01:44 PM Bank Kalteng (Phase 2) 2.30 hours (Support #1395 (Closed): [ESS Travel] Orgnization Level Direksi)
[ESS Travel] Orgnization Level Direksi M Azid Wahyudi
01:44 PM Bank Kalteng (Phase 2) 2.00 hours (Support #1400 (Closed): [ESS Travel] Task Condition)
[ESS Travel] Task Condition M Azid Wahyudi
01:43 PM Bank Kalteng (Phase 2) 1.00 hour (Support #1407 (Closed): [ESS Travel] - Settlement)
[ESS Travel] - Settlement M Azid Wahyudi
08:48 AM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/25/2022

06:53 PM Bank Kalteng (Phase 2) 2.00 hours (Support #1406 (Closed): [ESS Travel] - Validasi Requester)
[ESS Travel] - Validasi Requester M Azid Wahyudi
11:38 AM Bank Kalteng (Phase 2) 1.00 hour (Support #1401 (Closed): [ESS Travel] Delete Button Add Delete)
[ESS Travel] Delete Button Add Delete M Azid Wahyudi
11:27 AM Bank Kalteng (Phase 2) 2.30 hours (Project: Bank Kalteng (Phase 2))
Report Bank Aceh (All Employee & Years Of Service) M Azid Wahyudi

07/22/2022

05:20 PM Bank Kalteng (Phase 2) 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
05:17 AM Bank Kalteng (Phase 2) 2.30 hours (Bug #1398 (Closed): [Report PMS] Menampilkan Report PMS per Individu)
[Report PMS] Menampilkan Report PMS per Individu M Azid Wahyudi

07/21/2022

03:11 PM Bank Kalteng (Phase 2) 6.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/20/2022

11:15 PM Bank Kalteng (Phase 2) 1.00 hour (Feature #1388 (Closed): ESS Travel )
ESS Travel M Azid Wahyudi
05:18 PM Bank Kalteng (Phase 2) 2.00 hours (Bug #1372 (Closed): [HR-PMS] Data tidak Tampil di UI)
[HR-PMS] Data tidak Tampil di UI M Azid Wahyudi
10:34 AM 8.00 hours (Bug #1327 (Closed): [HR-COMPENSATION] Calculation masih ada yg kurang sesuai)
Fixing Report Compensation Tri Rizqiaty
09:44 AM 8.00 hours (Bug #1327 (Closed): [HR-COMPENSATION] Calculation masih ada yg kurang sesuai)
Fixing Compensation Calculate Tri Rizqiaty
09:38 AM 8.00 hours (Bug #1327 (Closed): [HR-COMPENSATION] Calculation masih ada yg kurang sesuai)
Fixing Compensation Calculate Tri Rizqiaty
10:31 AM Bank Kalteng (Phase 2) 8.00 hours (Bug #1203 (Closed): [Budgeting] Budget Calulation tidak bisa Execute)
Fixing Budget Calculation Tri Rizqiaty
10:21 AM Bank Kalteng (Phase 2) 4.00 hours (Bug #1203 (Closed): [Budgeting] Budget Calulation tidak bisa Execute)
Fixing Budget Calculation Tri Rizqiaty
10:29 AM Bank Kalteng (Phase 2) 8.00 hours (Bug #1352 (Closed): [HR Assessment] Data tidak ke save ke DB, sehingga tidak tampil di HR )
Fixing Assesment Tri Rizqiaty
09:49 AM 4.00 hours (Bug #1354 (Closed): [HR-BUDGET] Report Error)
Fixing Report Budget Tri Rizqiaty

07/19/2022

11:01 AM Bank Kalteng (Phase 2) 2.30 hours (Support #1362 (Closed): ESS Travel)
ESS Travel M Azid Wahyudi

07/18/2022

05:24 PM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Membuat Script UAT BKT Phase 2 dan Memperbaiki Settingan PMS Mega Yunita
01:50 PM Bank Kalteng (Phase 2) 2.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan
11:51 AM Bank Kalteng (Phase 2) 1.00 hour (Bug #1363 (Closed): [ESS PMS] PMS Review Phase 2 - Hilangkan Button Add & Delete)
[ESS PMS] PMS Review Phase 2 - Hilangkan Button Add & Delete M Azid Wahyudi
11:38 AM Bank Kalteng (Phase 2) 1.30 hour (Bug #1361 (Closed): Error Claim Status)
Error Claim Status M Azid Wahyudi
10:05 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS BKT Phase 2 Mega Yunita
10:05 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS BKT Phase 2 Mega Yunita
10:03 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS di project BKT Mega Yunita
10:03 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
09:57 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS di project BKT Mega Yunita

07/15/2022

05:09 PM 8.00 hours (Project: BANK KALTENG)
ESS - Travel Johanes Christian Kurni
03:59 PM Bank Kalteng (Phase 2) 7.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/14/2022

06:11 PM 8.00 hours (Project: BANK KALTENG)
ESS - Travel Johanes Christian Kurni
05:00 PM Bank Kalteng (Phase 2) 2.00 hours (Bug #1274 (Closed): [ESS PMS] Validasi KPI Score di PMS Final)
[ESS PMS] Validasi KPI Score di PMS Final M Azid Wahyudi
02:56 PM Bank Kalteng (Phase 2) 3.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan

07/13/2022

03:06 PM Bank Kalteng (Phase 2) 2.30 hours (Feature #1353 (Closed): kalkulasi pada form travel)
kalkulasi pada form travel M Azid Wahyudi

07/12/2022

05:50 PM 8.00 hours (Project: BANK KALTENG)
ESS - Travel Johanes Christian Kurni
 

Also available in: Atom