02/18/2022

05:01 PM 5.00 hours (Feature #882 (Closed): [Report Payroll] Report Akumulasi Cuti Tahunan dan Cuti Besar)
Create Report Bekal Cuti BKT Tri Rizqiaty
04:58 PM 3.00 hours (Feature #882 (Closed): [Report Payroll] Report Akumulasi Cuti Tahunan dan Cuti Besar)
Create Report Bekal Cuti BKT Tri Rizqiaty
11:18 AM 2.00 hours (Project: BANK KALTENG)
Membuat FRD Project PERTALIFE Mega Yunita
11:17 AM 2.00 hours (Project: BANK KALTENG)
Setting PMS di project BKT Mega Yunita
11:16 AM 4.00 hours (Project: BANK KALTENG)
Setting PMS di project Pertalife Mega Yunita
11:16 AM 4.00 hours (Project: BANK KALTENG)
Setting PMS di project BKT Mega Yunita
11:15 AM 4.00 hours (Project: BANK KALTENG)
Setting PMS di project Pertalife Mega Yunita

02/15/2022

04:47 PM 4.00 hours (Project: BANK KALTENG)
Setting PMS di project Pertalife Mega Yunita
03:11 PM 4.00 hours (Project: BANK KALTENG)
Setting PMS di project Pertalife Mega Yunita
10:00 AM 0.30 hour (Project: BANK KALTENG)
Membuat User dan menentukan role untuk Project BKT Mega Yunita

02/14/2022

05:32 PM 2.00 hours (Project: BANK KALTENG)
Setting PMS di project Pertalife Mega Yunita
05:32 PM 2.00 hours (Project: BANK KALTENG)
Testing BKT Mega Yunita
01:54 PM 4.00 hours (Project: BANK KALTENG)
Monitoring redmine dan QA Test Mega Yunita

02/11/2022

04:59 PM 4.00 hours (Project: BANK KALTENG)
Testing Project BKT Mega Yunita
04:06 PM 4.00 hours (Project: BANK KALTENG)
Testing dan memperbaiki settingan Time Management dan HR Administration project BKT Mega Yunita
04:05 PM 4.00 hours (Project: BANK KALTENG)
Memperbaiki settingan setelah UAT Bank Kalteng Mega Yunita

02/10/2022

03:08 PM 1.00 hour (Project: BANK KALTENG)
Memperbaiki settingan BKT Mega Yunita
03:07 PM 1.00 hour (Project: BANK KALTENG)
Memperbaiki settingan BKT Mega Yunita
03:07 PM 2.00 hours (Project: BANK KALTENG)
Memperbaiki settingan setelah UAT Bank Kalteng Mega Yunita
02:38 PM 1.00 hour (Feature #727 (Closed): Time Management - Late)
Time Management - Late M Azid Wahyudi

02/09/2022

05:31 PM 4.00 hours (Project: BANK KALTENG)
Testing dan Setting Parameter BKT Mega Yunita
01:58 PM 2.00 hours (Project: BANK KALTENG)
Testing PMS BKT Mega Yunita
01:58 PM 2.00 hours (Project: BANK KALTENG)
Setting Parameter Bank Kalteng Mega Yunita
09:36 AM 4.00 hours (Project: BANK KALTENG)
Testing dan Input data PMS BKT Mega Yunita

02/08/2022

03:01 PM 3.00 hours (Project: BANK KALTENG)
Testing UI Baru BBG Mega Yunita
02:59 PM 1.00 hour (Project: BANK KALTENG)
Membuat User Manual BKT Mega Yunita

02/07/2022

05:49 PM 2.00 hours (Project: BANK KALTENG)
Membuat User Manual BKT Mega Yunita
05:48 PM 2.00 hours (Project: BANK KALTENG)
Membuat User Manual BKT Mega Yunita
02:44 PM 2.00 hours (Project: BANK KALTENG)
Input data dan testing request PMS BKT Mega Yunita
02:43 PM 2.00 hours (Project: BANK KALTENG)
Setting dan memperbarui Wage Type BKT Mega Yunita

02/04/2022

05:50 PM 1.00 hour (Project: BANK KALTENG)
Setting dan Testing PMS BKT Mega Yunita
05:44 PM 3.00 hours (Project: BANK KALTENG)
Meeting dengak BKT terkait KPI dan PMS Mega Yunita
05:43 PM 4.00 hours (Project: BANK KALTENG)
Testing UI Baru BBG dan Arita Mega Yunita
05:43 PM 2.00 hours (Project: BANK KALTENG)
Meeting Internal dan Sharing Session Mega Yunita
05:41 PM 2.00 hours (Project: BANK KALTENG)
Testing Arita Mega Yunita
05:40 PM 0.60 hour (Feature #852 (Closed): [Header])
Setting Header ke Developer Mega Yunita

02/03/2022

04:39 PM 2.00 hours (Feature #836 (Closed): [Payroll Report] 1721 A1 2014 Personal)
Report M Azid Wahyudi
12:54 PM 2.00 hours (Feature #836 (Closed): [Payroll Report] 1721 A1 2014 Personal)
Report M Azid Wahyudi
12:04 PM 2.00 hours (Feature #831 (Closed): [Payroll Report] Wage Type Recap)
Report M Azid Wahyudi
11:21 AM 2.00 hours (Project: BANK KALTENG)
Testing UI Baru BBG Mega Yunita
11:20 AM 2.00 hours (Project: BANK KALTENG)
Meeting dengan PT. Pertalife Mega Yunita
11:19 AM 1.00 hour (Project: BANK KALTENG)
Memperbaiki settingan setelah UAT Bank Kalteng Mega Yunita
11:19 AM 1.00 hour (Project: BANK KALTENG)
Meeting dengan PT. Pertalife Mega Yunita
11:18 AM 2.00 hours (Project: BANK KALTENG)
Meeting dengan BKT Mega Yunita
11:16 AM 4.00 hours (Project: BANK KALTENG)
Testing UI Baru BBG Mega Yunita
11:15 AM 4.00 hours (Project: BANK KALTENG)
Memperbaiki settingan setelah UAT Bank Kalteng Mega Yunita
11:14 AM 4.00 hours (Project: BANK KALTENG)
Memperbaiki settingan setelah UAT Bank Kalteng Mega Yunita

02/02/2022

12:05 PM 3.00 hours (Feature #815 (Closed): [Report Payslip])
M Azid Wahyudi

01/31/2022

09:56 AM 4.00 hours (Project: BANK KALTENG)
Testing UI Baru BBG Mega Yunita
09:56 AM 4.00 hours (Project: BANK KALTENG)
Setting Job Catalog Bank Kalteng dan Standby untuk backup UAT BKT Mega Yunita

01/27/2022

05:55 PM 4.00 hours (Project: BANK KALTENG)
Stay UAT dan Setting Job Catalog Bank Kalteng Mega Yunita
05:55 PM 4.00 hours (Project: BANK KALTENG)
Setting Job Catalog Bank Kalteng Mega Yunita
11:25 AM 4.00 hours (Project: BANK KALTENG)
Setting Mapping Job dan Qualification Bank Kalteng Mega Yunita
11:24 AM 3.00 hours (Project: BANK KALTENG)
Setting Mapping Job dan Qualification Mega Yunita
11:23 AM 1.00 hour (Project: BANK KALTENG)
Membuat User Login untuk UAT BKT Mega Yunita
11:22 AM 4.00 hours (Project: BANK KALTENG)
Setting Leave BKT Mega Yunita
11:21 AM 4.00 hours (Project: BANK KALTENG)
Setting Organization Structure Mega Yunita
11:20 AM 5.00 hours (Project: BANK KALTENG)
Setting Mapping Job Catalog dan KPI Bank Kalteng Mega Yunita

01/26/2022

04:54 PM 1.00 hour (Feature #600 (Closed): TM to Payroll (Bekal Cuti Besar) )
Create Figure Cuti Besar BKT Tri Rizqiaty
04:31 PM 3.50 hours (Feature #600 (Closed): TM to Payroll (Bekal Cuti Besar) )
Create Figure Cuti Besar BKT Tri Rizqiaty

01/25/2022

05:59 PM 1.00 hour (Feature #599 (Closed): TM to Payroll (Bekal Cuti Tahunan))
Create Figure Cuti Tahunan BKT Tri Rizqiaty
03:17 PM 3.50 hours (Feature #646 (Closed): [Employee Administration] Custom External ID)
Create ExternalID in Wizard & MD Employee Tri Rizqiaty
09:22 AM 0.50 hour (Project: BANK KALTENG)
Debug External ID BKT Tri Rizqiaty

01/24/2022

04:28 PM 0.50 hour (Project: BANK KALTENG)
Support Report Bank Transfer BKT Tri Rizqiaty
11:15 AM 1.00 hour (Project: BANK KALTENG)
Setting Menu Mega Yunita
11:13 AM 2.00 hours (Project: BANK KALTENG)
Setting Job Catalog Bank Kalteng Mega Yunita
11:13 AM 4.00 hours (Project: BANK KALTENG)
Melakukan setting dan testing untuk periapan UAT Project Bank Kalteng Mega Yunita
11:12 AM 5.00 hours (Project: BANK KALTENG)
Melakukan setting dan testing untuk periapan UAT Project Bank Kalteng Mega Yunita

01/21/2022

06:05 PM 4.00 hours (Project: BANK KALTENG)
Membuat validasi untuk pengajuan leave dengan developer pada project Bank Kaalteng Mega Yunita
06:03 PM 4.00 hours (Project: BANK KALTENG)
Setting Organization Structure Mega Yunita
05:44 PM 4.00 hours (Feature #599 (Closed): TM to Payroll (Bekal Cuti Tahunan))
Figure Cuti Tahunan BKT Tri Rizqiaty
05:42 PM 2.50 hours (Project: BANK KALTENG)
Fixing Enginge Execute TM To PY BKT Tri Rizqiaty

01/20/2022

05:57 PM 0.50 hour (Feature #599 (Closed): TM to Payroll (Bekal Cuti Tahunan))
Setting Parameter TM To PY GenParam Tri Rizqiaty
05:50 PM 8.00 hours (Project: BANK KALTENG)
UAT Script Preparation Anonymous
05:49 PM 8.00 hours (Project: BANK KALTENG)
UAT Script Preparation Anonymous
04:46 PM 4.00 hours (Project: BANK KALTENG)
Membuat Redmine untuk Bank Transfer, Payslip Mega Yunita
04:44 PM 4.00 hours (Project: BANK KALTENG)
Setting Job Catalog Bank Kalteng Mega Yunita
 