Project

General

Profile

Activity

From 06/30/2022 to 07/29/2022

07/29/2022

04:20 PM 1.30 hour (Bug #1377 (Closed): [HR - Training Management] Nama Office tidak sesuai)
[HR - Training Management] Nama Office tidak sesuai M Azid Wahyudi
02:52 PM 5.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/28/2022

06:41 PM 8.00 hours (Project: Bank Kalteng (Phase 2))
aceh (Support request Client) , BKT (PMS goal setting , review , final & travel) , BMS(Travel editGrid for web mobile... M Azid Wahyudi
06:36 PM 2.00 hours (Support #1399 (Closed): [ESS Travel] Mail Notif Supervisor)
[ESS Travel] Mail Notif Supervisor M Azid Wahyudi
02:56 PM 8.00 hours (Project: Bank Kalteng (Phase 2))
Pendampingan Trial Phase 1 BKT Fachrul Hardianto
02:55 PM 8.00 hours (Project: Bank Kalteng (Phase 2))
Pendampingan Trial Phase 1 BKT Fachrul Hardianto
02:49 PM 2.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Meeting Progress BKT Fachrul Hardianto
02:48 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan meeting Pre-UAT Bank Kalteng modul Talent & Training Fachrul Hardianto
02:41 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom meeting Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:39 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom meeting Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:39 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan Pre-UAT Bank Kalteng modul PMS & Compensation Fachrul Hardianto
02:32 PM 4.00 hours (Project: Bank Kalteng (Phase 2))
Testing & Persiapan Pre-UAT Bank Kalteng modul Budgeting & Recruitment Fachrul Hardianto
02:31 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Pre-UAT Bank Kalteng modul Budgeting & Recruitment Fachrul Hardianto
02:27 PM 4.00 hours (Project: Bank Kalteng (Phase 2))
Testing & preparation PRE-UAT Mecical & Travel Fachrul Hardianto
02:24 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
Zoom Bank Kalteng Pre-UAT Modul Medical & Travel Fachrul Hardianto
12:13 PM 4.00 hours (Feature #1402 (Closed): [ESS PMS] Bobot Perhitungan KPI dan Competency)
[ESS PMS] Bobot Perhitungan KPI dan Competency M Azid Wahyudi

07/27/2022

11:43 AM 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
09:47 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
ess travel , PMS , report2 M Azid Wahyudi

07/26/2022

04:54 PM 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
04:54 PM 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan
01:44 PM 2.30 hours (Support #1395 (Closed): [ESS Travel] Orgnization Level Direksi)
[ESS Travel] Orgnization Level Direksi M Azid Wahyudi
01:44 PM 2.00 hours (Support #1400 (Closed): [ESS Travel] Task Condition)
[ESS Travel] Task Condition M Azid Wahyudi
01:43 PM 1.00 hour (Support #1407 (Closed): [ESS Travel] - Settlement)
[ESS Travel] - Settlement M Azid Wahyudi
08:48 AM 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/25/2022

06:53 PM 2.00 hours (Support #1406 (Closed): [ESS Travel] - Validasi Requester)
[ESS Travel] - Validasi Requester M Azid Wahyudi
11:38 AM 1.00 hour (Support #1401 (Closed): [ESS Travel] Delete Button Add Delete)
[ESS Travel] Delete Button Add Delete M Azid Wahyudi
11:27 AM 2.30 hours (Project: Bank Kalteng (Phase 2))
Report Bank Aceh (All Employee & Years Of Service) M Azid Wahyudi

07/22/2022

05:20 PM 4.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan
05:17 AM 2.30 hours (Bug #1398 (Closed): [Report PMS] Menampilkan Report PMS per Individu)
[Report PMS] Menampilkan Report PMS per Individu M Azid Wahyudi

07/21/2022

03:11 PM 6.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/20/2022

11:15 PM 1.00 hour (Feature #1388 (Closed): ESS Travel )
ESS Travel M Azid Wahyudi
05:18 PM 2.00 hours (Bug #1372 (Closed): [HR-PMS] Data tidak Tampil di UI)
[HR-PMS] Data tidak Tampil di UI M Azid Wahyudi
10:31 AM 8.00 hours (Bug #1203 (Closed): [Budgeting] Budget Calulation tidak bisa Execute)
Fixing Budget Calculation Tri Rizqiaty
10:21 AM 4.00 hours (Bug #1203 (Closed): [Budgeting] Budget Calulation tidak bisa Execute)
Fixing Budget Calculation Tri Rizqiaty
10:29 AM 8.00 hours (Bug #1352 (Closed): [HR Assessment] Data tidak ke save ke DB, sehingga tidak tampil di HR )
Fixing Assesment Tri Rizqiaty

07/19/2022

11:01 AM 2.30 hours (Support #1362 (Closed): ESS Travel)
ESS Travel M Azid Wahyudi

07/18/2022

05:24 PM 8.00 hours (Project: Bank Kalteng (Phase 2))
Membuat Script UAT BKT Phase 2 dan Memperbaiki Settingan PMS Mega Yunita
01:50 PM 2.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan
11:51 AM 1.00 hour (Bug #1363 (Closed): [ESS PMS] PMS Review Phase 2 - Hilangkan Button Add & Delete)
[ESS PMS] PMS Review Phase 2 - Hilangkan Button Add & Delete M Azid Wahyudi
11:38 AM 1.30 hour (Bug #1361 (Closed): Error Claim Status)
Error Claim Status M Azid Wahyudi
10:05 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS BKT Phase 2 Mega Yunita
10:05 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS BKT Phase 2 Mega Yunita
10:03 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS di project BKT Mega Yunita
10:03 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
10:02 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Testing BKT dan Setting Phase 2 Mega Yunita
09:57 AM 8.00 hours (Project: Bank Kalteng (Phase 2))
Setting PMS di project BKT Mega Yunita

07/15/2022

03:59 PM 7.00 hours (Project: Bank Kalteng (Phase 2))
ESS Travel Fiona Avangeline Jonathan

07/14/2022

05:00 PM 2.00 hours (Bug #1274 (Closed): [ESS PMS] Validasi KPI Score di PMS Final)
[ESS PMS] Validasi KPI Score di PMS Final M Azid Wahyudi
02:56 PM 3.00 hours (Project: Bank Kalteng (Phase 2))
ESS Medical Fiona Avangeline Jonathan

07/13/2022

03:06 PM 2.30 hours (Feature #1353 (Closed): kalkulasi pada form travel)
kalkulasi pada form travel M Azid Wahyudi

07/07/2022

02:38 PM 8.00 hours (Bug #1203 (Closed): [Budgeting] Budget Calulation tidak bisa Execute)
Fixing Budget Calculation Tri Rizqiaty

07/06/2022

05:08 PM 1.00 hour (Bug #1297 (Closed): [ESS] - Travel)
[ESS] - Travel M Azid Wahyudi
04:16 PM 2.00 hours (Feature #1295 (Closed): [ESS PMS] PMS Final Phase 2)
[ESS PMS] PMS Final Phase 2 M Azid Wahyudi
03:28 PM 4.00 hours (Feature #1291 (Closed): [ESS PMS] PMS Review Phase 2)
[ESS PMS] PMS Review Phase 2 M Azid Wahyudi

07/01/2022

05:31 PM 1.00 hour (Bug #1308 (Closed): [HR PMS] Hide Action Add)
Fixing Hide Button PMS HR Tri Rizqiaty
05:23 PM 6.00 hours (Bug #1308 (Closed): [HR PMS] Hide Action Add)
Fixing Hide Button PMS HR Tri Rizqiaty
 

Also available in: Atom