ESS Travel - Kolom Grid Total Cost di perlebar

Added by Mr Ikmal about 1 month ago. Updated 28 days ago.

Status:
Deploy
Priority:
Normal
Assignee:
Start date:
09/17/2025
Due date:
09/18/2025 (41 days late)
% Done:

0%

Estimated time:
Spent time:

Description

Dear mas Azid,

Mohon bantuannya untuk memperlebar kolom di grid Total Cost pada ESS Travel (request dari client), agar tulisan di dalamnya dapat terlihat dengan jelas.

Terima kasih.

PORT DEV : http://remote.minovais.com:61139/
DB : remote.minovais.com, 1468
Nama DB : MinovaES_BIA_BaseServerCloud


Files

#1

Updated by Kezia Pawitra Yulianti about 1 month ago

  • Due date set to 09/18/2025
  • Status changed from New to Assigned
#2

Updated by M Azid Wahyudi 29 days ago

  • Status changed from Assigned to QA Test
  • Assignee changed from M Azid Wahyudi to Mr Ikmal

dear ikmal , udah bisa di test semua ya kecuali no 1 itu kan bisa lebih dari satu kalau dia 2 record dengan tanggal yang berbeda gimana jadi di samain semua tanggalnya ?

package :
bizproc(afterrender,beforesubmit,init,method)

messagecatalog (TESTEROR,VALOVRDT)

makasih

#3

Updated by Mr Ikmal 29 days ago

Ok mas, sudah di deploy ya. Terima kasih

#4

Updated by Mr Ikmal 29 days ago

Dear mas azid,
Sementara Ok tapi dgn catatan -> Ini gw test pas task karyawan yg create kolom nya udah ok mas, tapi kenapa di task approval atasan kolom nya jadi seperti awal lagi ya mas? kira2 bisa diakomodir kalau di semua task ga mas, di karyawan dan atasan? (Contoh : RegID 1752).
Contoh terlampir;

#5

Updated by M Azid Wahyudi 28 days ago

  • Status changed from Revise to QA Test
  • Assignee changed from M Azid Wahyudi to Mr Ikmal

dear ikmal , udah bisa di test ya

package :
bizproc(method)

makasih

#6

Updated by Mr Ikmal 28 days ago

  • Status changed from QA Test to Deploy

Sudah ok mas dan sudah di deploy ya.