Bug #3661

Perbaikan Performance Appraisal

Added by haykal haykal about 1 month ago. Updated 25 days ago.

Status:
QA Test
Priority:
Immediate
Assignee:
Start date:
06/10/2025
Due date:
06/12/2025 (39 days late)
% Done:

0%

Estimated time:
Spent time:

Description

Dear Azid,

Untk di menu Performance Appraisal ingin ada beberapa perbaikan ya:

1. Field Appraisal Period tidak terisi (Foto 1). Harusnya otomatis terisi berdasarkan Appraisal Period yang telah diisikan karyawan di ESS nya (01 Jan - 31 Des 2025)
2. Bagian Hasil Kerja (KPI) yang muncul cuma ada 1 KPI (Foto 2). Padahal harusnya 6. Kalau dicek di PHRPA0049 data KPI nya sudah masuk semua. Tolong diperbaiki ya.

Contoh: EmployeeID 00000855 utk Goal Setting 2025

Terima kasih.

Menu Path: Human Resource > HR Strategic > Performance Management > Performance Appraisal
Port: http://remote.minovais.com:61133/
DB: MinovaES_BankKalteng_BaseServerProd (di 1452)


Files

#1

Updated by Kezia Pawitra Yulianti about 1 month ago

  • Due date set to 06/12/2025
  • Status changed from New to Assigned
  • Priority changed from Normal to Immediate
#2

Updated by M Azid Wahyudi about 1 month ago

ini HR

#3

Updated by M Azid Wahyudi about 1 month ago

  • Status changed from Assigned to QA Test
  • Assignee changed from M Azid Wahyudi to haykal haykal

dear haykal , udah bisa di test ya

package :
settingan di sdatatablefield pada table PDSPM0001, trigger combonya di ilangin

makasih

#4

Updated by M Azid Wahyudi about 1 month ago

pada field appraiserType

#5

Updated by M Azid Wahyudi about 1 month ago

sama untuk yang KPI itu karena isSubKPI NULL ini nanti gw cek flow fieldposting nanti kalau engga stabil datanya di runbiz di kondisi terakhir fieldpos gw isi 0 aja jika ada null di table isSubKPI

#6

Updated by haykal haykal 26 days ago

Dear Azid,

Untk posisi Direct Supervisor 1 dan Direct Supervisor 2 di bagian Penilai tlg dituker ya.. (foto diattach)

Jadi yg Direct Supervisor 1 pengennya diatas.

Contoh: PMS Review January-April 2025 EmployeeID 00000047

Terimakasih.

#7

Updated by haykal haykal 26 days ago

Dear Azid,

Untk PMS Review January-April 2025 EmployeeID 00000047 saya lihat yg bagian Hasil Kerja (KPI) tidak muncul (foto diattach)

Padahal kalau saya lihat di PHRPA0049 ada datanya.

ReqID: 1384125

Tolong bantu dicek dan diperbaiki ya.

Terimakasih.

#8

Updated by M Azid Wahyudi 25 days ago

  • Status changed from Assigned to QA Test
  • Assignee changed from M Azid Wahyudi to haykal haykal

dear haykal , udah bisa di test ya

makasih