Fiona Avangeline Jonathan's activity
From 05/24/2022 to 06/22/2022
06/22/2022
- 05:43 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 09:42 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
- ESS Medical
06/20/2022
- 05:19 PM PT BMS MIGRATION & ENHANCEMENT 4.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Mutation
- 01:56 PM BANK KALTENG 4.00 hours (Project: BANK KALTENG)
- Data Migration
06/17/2022
- 05:13 PM BANK KALTENG 1.00 hour (Project: BANK KALTENG)
- Data Migration
- 05:12 PM PT BMS MIGRATION & ENHANCEMENT 7.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Mutation
06/16/2022
- 05:01 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 05:01 PM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
- Sharing Modul HR
- 05:00 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Mutation
06/14/2022
- 05:10 PM PT BMS MIGRATION & ENHANCEMENT 3.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Mutation
- 03:57 PM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
- Meeting Karyawan
- 02:20 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 01:48 PM PT ARITA 1.00 hour (Project: PT ARITA)
- Generate User Login
06/13/2022
- 05:34 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Mutation
06/10/2022
- 03:44 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 09:00 AM BANK KALTENG 2.00 hours (Project: BANK KALTENG)
- Testing Import Data
- 08:59 AM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
06/09/2022
- 10:31 AM Minova ERP Internal 1.30 hour (Project: Minova ERP Internal)
- Ujian Sertifikasi
06/08/2022
- 05:03 PM PT BMS MIGRATION & ENHANCEMENT 6.30 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 09:04 AM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
- Project Management Sharing
- 09:04 AM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
06/06/2022
- 04:19 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
06/03/2022
- 04:56 PM PT ARITA 1.00 hour (Project: PT ARITA)
- Support Go Live
- 04:31 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 02:16 PM MINOVAES - PRODUCT 5.00 hours (Project: MINOVAES - PRODUCT)
- Website MINOVA
06/02/2022
- 04:16 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 02:33 PM MINOVAES - PRODUCT 6.00 hours (Project: MINOVAES - PRODUCT)
- Design Mock up BI Dashboard
05/31/2022
- 04:49 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 03:57 PM MINOVAES - PRODUCT 2.00 hours (Project: MINOVAES - PRODUCT)
- Design Mock up BI Dashboard
05/30/2022
- 05:44 PM MINOVAES - PRODUCT 4.00 hours (Project: MINOVAES - PRODUCT)
- Design Mock up BI Dashboard
- 02:53 PM PT ARITA 1.00 hour (Project: PT ARITA)
- Generate User Login
- 01:24 PM Minova ERP Internal 3.00 hours (Project: Minova ERP Internal)
- Training
05/27/2022
- 05:46 PM PT ARITA 3.00 hours (Project: PT ARITA)
- Data Migration
- 04:55 PM PT BMS MIGRATION & ENHANCEMENT 3.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
- ESS Exit Clearance
- 10:43 AM BANK KALTENG 1.00 hour (Project: BANK KALTENG)
- Mapping Data Bank Kalteng
- 10:43 AM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
- Design
05/25/2022
- 04:28 PM BANK KALTENG 4.00 hours (Project: BANK KALTENG)
- Mapping Data Bank Kalteng
- 04:04 PM Minova ERP Internal 3.00 hours (Project: Minova ERP Internal)
- Training
- 03:38 PM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
- Design
05/24/2022
- 06:06 PM PT ARITA 5.00 hours (Project: PT ARITA)
- Mapping Data Tambahan PA02
- 03:09 PM MINOVAES - PRODUCT 2.00 hours (Project: MINOVAES - PRODUCT)
- Website MINOVA
- 10:38 AM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
- Revisi Design Mock up BI Dashboard
Also available in: Atom