Fiona Avangeline Jonathan's activity
From 05/24/2022 to 06/22/2022
06/22/2022
- 05:43 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 09:42 AM Bank Kalteng (Phase 2) 8.00 hours (Project: Bank Kalteng (Phase 2))
 - ESS Medical
 
06/20/2022
- 05:19 PM PT BMS MIGRATION & ENHANCEMENT 4.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Mutation
 - 01:56 PM BANK KALTENG 4.00 hours (Project: BANK KALTENG)
 - Data Migration
 
06/17/2022
- 05:13 PM BANK KALTENG 1.00 hour (Project: BANK KALTENG)
 - Data Migration
 - 05:12 PM PT BMS MIGRATION & ENHANCEMENT 7.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Mutation
 
06/16/2022
- 05:01 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 05:01 PM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
 - Sharing Modul HR
 - 05:00 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Mutation
 
06/14/2022
- 05:10 PM PT BMS MIGRATION & ENHANCEMENT 3.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Mutation
 - 03:57 PM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
 - Meeting Karyawan
 - 02:20 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 01:48 PM PT ARITA 1.00 hour (Project: PT ARITA)
 - Generate User Login
 
06/13/2022
- 05:34 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Mutation
 
06/10/2022
- 03:44 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 09:00 AM BANK KALTENG 2.00 hours (Project: BANK KALTENG)
 - Testing Import Data
 - 08:59 AM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 
06/09/2022
- 10:31 AM Minova ERP Internal 1.30 hour (Project: Minova ERP Internal)
 - Ujian Sertifikasi
 
06/08/2022
- 05:03 PM PT BMS MIGRATION & ENHANCEMENT 6.30 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 09:04 AM Minova ERP Internal 2.00 hours (Project: Minova ERP Internal)
 - Project Management Sharing
 - 09:04 AM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 
06/06/2022
- 04:19 PM PT BMS MIGRATION & ENHANCEMENT 8.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 
06/03/2022
- 04:56 PM PT ARITA 1.00 hour (Project: PT ARITA)
 - Support Go Live
 - 04:31 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 02:16 PM MINOVAES - PRODUCT 5.00 hours (Project: MINOVAES - PRODUCT)
 - Website MINOVA
 
06/02/2022
- 04:16 PM PT BMS MIGRATION & ENHANCEMENT 2.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 02:33 PM MINOVAES - PRODUCT 6.00 hours (Project: MINOVAES - PRODUCT)
 - Design Mock up BI Dashboard
 
05/31/2022
- 04:49 PM PT BMS MIGRATION & ENHANCEMENT 6.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 03:57 PM MINOVAES - PRODUCT 2.00 hours (Project: MINOVAES - PRODUCT)
 - Design Mock up BI Dashboard
 
05/30/2022
- 05:44 PM MINOVAES - PRODUCT 4.00 hours (Project: MINOVAES - PRODUCT)
 - Design Mock up BI Dashboard
 - 02:53 PM PT ARITA 1.00 hour (Project: PT ARITA)
 - Generate User Login
 - 01:24 PM Minova ERP Internal 3.00 hours (Project: Minova ERP Internal)
 - Training
 
05/27/2022
- 05:46 PM PT ARITA 3.00 hours (Project: PT ARITA)
 - Data Migration
 - 04:55 PM PT BMS MIGRATION & ENHANCEMENT 3.00 hours (Project: PT BMS MIGRATION & ENHANCEMENT)
 - ESS Exit Clearance
 - 10:43 AM BANK KALTENG 1.00 hour (Project: BANK KALTENG)
 - Mapping Data Bank Kalteng
 - 10:43 AM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
 - Design
 
05/25/2022
- 04:28 PM BANK KALTENG 4.00 hours (Project: BANK KALTENG)
 - Mapping Data Bank Kalteng
 - 04:04 PM Minova ERP Internal 3.00 hours (Project: Minova ERP Internal)
 - Training
 - 03:38 PM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
 - Design
 
05/24/2022
- 06:06 PM PT ARITA 5.00 hours (Project: PT ARITA)
 - Mapping Data Tambahan PA02
 - 03:09 PM MINOVAES - PRODUCT 2.00 hours (Project: MINOVAES - PRODUCT)
 - Website MINOVA
 - 10:38 AM MINOVAES - PRODUCT 1.00 hour (Project: MINOVAES - PRODUCT)
 - Revisi Design Mock up BI Dashboard
 
Also available in: Atom