ericsson ericsson's activity
From 12/05/2021 to 01/03/2022
01/03/2022
- 12:43 PM PT BMS MIGRATION & ENHANCEMENT Feature #675: [ PA ] - Report Performance History
- closed ndo
- 12:38 PM PT BMS MIGRATION & ENHANCEMENT Bug #681 (Closed): [ HR ] - Skills Report
- 12:34 PM PT BMS MIGRATION & ENHANCEMENT Feature #683: [ PA ] - Report Employee Assignment
- udah disesuaikan zid.
langsung eksekusi yoo... - 09:26 AM PT BMS MIGRATION & ENHANCEMENT Feature #673: [ PA ] Report Personal Data
- Dear, Mang azid.
untuk report personal data, masih ada data yang belum ketarik, diantaranya :
1. Religion
2. KTP...
12/30/2021
- 02:39 PM RSM Phase II Feature #707 (Assigned): [ESS] - PMS - PE - Flow Action Approve
- 02:39 PM RSM Phase II Feature #707 (Closed): [ESS] - PMS - PE - Flow Action Approve
- Dear, Developer.
Mohon bantuannya, untuk Flow action approve pada individual assignment evaluation tidak membaca d... - 11:50 AM RSM Phase II Feature #705 (Assigned): [ESS] - PMS - PE - Parameter task mail to partner & task mail to partner 2
- 11:41 AM RSM Phase II Feature #705 (Closed): [ESS] - PMS - PE - Parameter task mail to partner & task mail to partner 2
- Dear, Developer.
Mohon dibuatkan parameter untuk TaskID= mail_to_partner & mail_to_partner_2 dengan detail sebagai... - 11:33 AM RSM Phase II Feature #704 (Assigned): [ESS] - PMS - PE - Parameter task mail to manager
- 11:32 AM RSM Phase II Feature #704 (Closed): [ESS] - PMS - PE - Parameter task mail to manager
- Dear, Developer.
Mohon dibuatkan parameter untuk TaskID= mail_to_manager dengan detail sebagai berikut :
taskID...
12/28/2021
- 04:14 PM BANK MEGA SYARIAH - ES Feature #665: BMS - ES , Costum Menu
- mang, Azid untuk yang nomer 2 = report terminasi.
nama menuID = CPAR31
!clipboard-202112281613-ifaxv.png!
- 03:45 PM RSM Phase II Feature #694 (Assigned): [ESS] - PMS - PE - Parameter Approval Partner
- 03:45 PM RSM Phase II Feature #694 (Closed): [ESS] - PMS - PE - Parameter Approval Partner
- Dear, Developer.
Mohon dibuatkan parameter untuk TaskID= apv_partner dengan detail sebagai berikut :
taskID : a... - 03:29 PM RSM Phase II Feature #692 (Assigned): [ESS] - PMS - PE - Parameter Task Condition
- 03:28 PM RSM Phase II Feature #692 (Closed): [ESS] - PMS - PE - Parameter Task Condition
- Dear, Developer.
Mohon dibuatkan parameter kondisi untuk membaca kondisi creator apakah posisinya sebagai manager ... - 02:22 PM RSM Phase II Support #418 (Closed): My Work Place - My Attendance Report (adjusment design seperti attendance monthly pada hr) #update
- 02:22 PM RSM Phase II Bug #653 (Closed): [ HR ] - Header Employee Master Data
- 02:21 PM RSM Phase II Feature #613 (Closed): [ESS]_Individual Development Evaluation _Engagement Information_Appraisal Criteria
- 02:19 PM RSM Phase II Feature #407 (Closed): RSM II - BI - Statistik Report (new dataset)
- 02:18 PM RSM Phase II Feature #315 (Closed): RSM II - General - Dashboard Widget (attendance) #widget
12/24/2021
- 06:06 PM PT BMS MIGRATION & ENHANCEMENT Feature #683 (Assigned): [ PA ] - Report Employee Assignment
- 06:06 PM PT BMS MIGRATION & ENHANCEMENT Feature #683 (Closed): [ PA ] - Report Employee Assignment
- Dear, Team Developer.
Mohon bantuannya untuk menambahkan field pada report Employee Assignment (ReportID=9000027)
... - 04:08 PM PT BMS MIGRATION & ENHANCEMENT Bug #681 (Closed): [ HR ] - Skills Report
- Dear, Team Developer.
Mohon bantuannya untuk menambahkan field pada report Skill (ReportID=9000037)
Berikut field...
12/23/2021
- 06:27 PM BANK MEGA SYARIAH - ES Feature #669 (Assigned): [ PMS ] - Report Custom PMS
- 10:58 AM BANK MEGA SYARIAH - ES Feature #669 (Closed): [ PMS ] - Report Custom PMS
- Dear, Developer.
Mohon Bantuannya untuk dibuatkan report custome untuk report berikut ini:
1. Report Performanc... - 06:26 PM BANK MEGA SYARIAH - ES Bug #658 (Assigned): BMS - ES
- 06:26 PM BANK MEGA SYARIAH - ES Feature #666 (Assigned): BMS - ES , Costum Menu Traning Management
- 06:26 PM BANK MEGA SYARIAH - ES Feature #665 (Assigned): BMS - ES , Costum Menu
- 06:25 PM BANK MEGA SYARIAH - ES Bug #664 (Assigned): BMS - ES , Payroll Accounting
- 06:23 PM BANK MEGA SYARIAH - ES Feature #671 (Assigned): [ PA ] - Report Employee Movement - Customized BMS
- 06:23 PM PT BMS MIGRATION & ENHANCEMENT Feature #675 (Closed): [ PA ] - Report Performance History
- Dear, Team Developer.
Mohon bantuannya untuk menambahkan field pada report Performance History (ReportID=99000040)... - 04:42 PM PT BMS MIGRATION & ENHANCEMENT Feature #673 (Assigned): [ PA ] Report Personal Data
- 04:41 PM PT BMS MIGRATION & ENHANCEMENT Feature #673 (Closed): [ PA ] Report Personal Data
- Dear, Team Developer.
Mohon bantuannya untuk menambahkan field pada report personal data (ReportID=9000026)
Berik...
12/21/2021
- 10:12 AM RSM Phase II Bug #651 (Closed): [Payslip] - Size Logo dan size detail alamat
- 10:12 AM RSM Phase II Bug #652 (Closed): [Payslip] - Font payslip
- 10:11 AM RSM Phase II Bug #641 (Closed): [ Widget ] - Tulisan pada Widget
- 10:00 AM RSM Phase II Bug #653 (Closed): [ HR ] - Header Employee Master Data
- Dear, Mang saswanto.
Mohon bantuannya, pada header employee master data, Field Level sekarang get datanya dari pos...
12/20/2021
- 07:24 PM RSM Phase II Bug #652 (Closed): [Payslip] - Font payslip
- Dear, Mang Azid.
Mohon bantuannya untuk report Payslip fontnya gunakan font jenis Arial.
!clipboard-20211220192... - 07:18 PM RSM Phase II Bug #651 (Closed): [Payslip] - Size Logo dan size detail alamat
- Dear, Mang Azid.
Mohon bantuannya,
Pada payslip RSM tolong pada logo RSM dan di tulisan Address RSM ukurannya tid... - 07:14 PM RSM Phase II Bug #629 (Closed): User Management - Master Data Profile
12/14/2021
- 08:27 PM RSM Phase II Bug #641 (Closed): [ Widget ] - Tulisan pada Widget
- Dear, mang saswanto.
Mohon bantuannya untuk merubah beberapa tulisan pada widget berikut ini.
1. Demography by ...
12/09/2021
- 05:14 PM RSM Phase II Feature #627 (Closed): Widget - HR Dashboard
- 10:37 AM RSM Phase II Feature #627 (Assigned): Widget - HR Dashboard
- 10:07 AM RSM Phase II Feature #627 (Closed): Widget - HR Dashboard
- Dear, pak sawanto.
Mohon Bantuannya untuk widget demography by level dirubah menjadi demography by LOB. Data bisa ... - 05:11 PM RSM Phase II Feature #628 (Closed): Widget - HR DashBoard
- 10:37 AM RSM Phase II Feature #628 (Assigned): Widget - HR DashBoard
- 10:33 AM RSM Phase II Feature #628 (Closed): Widget - HR DashBoard
- Dear, Mang Saswanto.
Dear, pak sawanto.
Mohon Bantuannya untuk widget demography by lEducation dirubah menjadi ... - 05:06 PM RSM Phase II Bug #629 (Closed): User Management - Master Data Profile
- Dear, Mang Saswanto.
Mohon bantuannya untuk memperbaiki bugs pada master data profil yang ada di user management, ... - 10:25 AM RSM Phase II Feature #611 (Closed): [ESS]_Performance Goal _ Individual Development Plan_Appraisal Criteria
- 10:24 AM RSM Phase II Feature #612 (Closed): [ESS]_Individual Development Evaluation _ To be completed by employee,supervisor_Appraisal Criteria
- 10:22 AM RSM Phase II Feature #610 (Closed): [ESS]_Performance Goal _ Goals_Appraisal Criteria
- 10:11 AM RSM Phase II Feature #622 (Closed): Delete Tombol Action
- 10:10 AM RSM Phase II Feature #623 (Closed): Widget
12/08/2021
- 02:59 PM RSM Phase II Bug #620 (Closed): User Management - Tombol Terpotong
- 10:39 AM RSM Phase II Bug #620 (Closed): User Management - Tombol Terpotong
- Dear, Team Developer.
Mohon Bantuannya untuk memperbaiki tampilan tombol pada saat akan saving proses upload foto ...
12/06/2021
- 06:36 PM RSM Phase II Feature #613: [ESS]_Individual Development Evaluation _Engagement Information_Appraisal Criteria
- !clipboard-202112061833-mnxs4.png!
Untuk Field Manager dan partner, lookUp dari table ROJECTENGAGEMENT dengan me... - 03:24 PM RSM Phase II Feature #613 (Assigned): [ESS]_Individual Development Evaluation _Engagement Information_Appraisal Criteria
- 03:23 PM RSM Phase II Feature #613 (Closed): [ESS]_Individual Development Evaluation _Engagement Information_Appraisal Criteria
- Dear, Team Developer.
Mohon bantuannya untuk ESS Individual Development Evaluation pada form Engagement Informatio... - 12:00 PM RSM Phase II Feature #612 (Closed): [ESS]_Individual Development Evaluation _ To be completed by employee,supervisor_Appraisal Criteria
Dear, Team Developer.
Mohon bantuannya untuk ESS Individual Development Evaluation pada form To be completed by ...- 10:41 AM RSM Phase II Feature #610 (Assigned): [ESS]_Performance Goal _ Goals_Appraisal Criteria
- 10:03 AM RSM Phase II Feature #610 (Closed): [ESS]_Performance Goal _ Goals_Appraisal Criteria
- Dear, Team Developer.
Mohon bantuannya untuk form goal setting pada form goal bisa get dari Appraisal kriteria per... - 10:41 AM RSM Phase II Feature #611 (Assigned): [ESS]_Performance Goal _ Individual Development Plan_Appraisal Criteria
- 10:38 AM RSM Phase II Feature #611 (Closed): [ESS]_Performance Goal _ Individual Development Plan_Appraisal Criteria
Dear, Team Developer.
Mohon bantuannya untuk form goal setting pada form Individual Development Plan bisa get da...
Also available in: Atom